Tasklist Rules
Default Work Structure
Use Basecamp To-dos as the default structure for planned project work. A To-do is the right unit when work has a clear action, owner, timing, and completion definition.
Use Card Table only for reactive or pipeline work, such as incoming requests, intake queues, review stages, sales-style pipelines, support flows, or work that moves through repeatable status columns before it is ready for a committed To-do list.
Assignment Rules
Every task set needs a named directly responsible individual (DRI). The DRI is accountable for keeping the task list coherent, resolving unclear ownership, and making sure work moves forward.
Use hybrid assignment:
- Near-term tasks need named owners.
- Dependency-critical tasks need named owners.
- Client-facing or approval-heavy tasks need named owners.
- Later uncertain work may use role placeholders, such as
Designer,Developer,Client reviewer, orLegal reviewer. - Each role placeholder needs a staffing-resolution task with a named owner and a date or milestone-relative trigger.
Due Date Rules
Use hybrid due dates:
- Use fixed dates for near-term work, dependency-critical work, launch-critical work, meetings, reviews, and external commitments.
- Use milestone-relative timing for later uncertain work, such as
3 business days after content approvalor1 week before launch. - Convert all milestone-relative timing to fixed Basecamp due dates before creating the final Basecamp To-dos.
- If timing is uncertain, name the decision point that will convert relative timing into fixed dates.
Task Output Contract
Each task should include:
- Title: Action-oriented, specific, and short.
- Owner: Named person or role placeholder.
- Owner type:
named DRI,named owner, orrole placeholder. - Timing type:
fixed date,milestone-relative, orsequence-only. - Due or relative timing: Date, milestone-relative timing, or ordering note.
- Description: Context needed to do the work without rereading the full plan.
- Done means: Observable completion condition.
- Dependency: Upstream task, decision, asset, approval, or
none. - Confidence:
high,medium, orlow, based on clarity of scope, owner, and timing.
Task Quality Checklist
Before creating To-dos in Basecamp, confirm that:
- To-dos are used for committed planned work.
- Card Table is reserved for reactive or pipeline work.
- A named DRI exists for the task list or project area.
- Near-term and dependency-critical tasks have named owners.
- Role placeholders are limited to later uncertain work.
- Every role placeholder has a staffing-resolution task.
- Fixed dates are used where commitments or dependencies require them.
- Milestone-relative timing has a clear conversion trigger.
- All Basecamp-ready tasks have fixed due dates where Basecamp dates are required.
- Each task states what done means.
- Dependencies are explicit or marked as none.
- Low-confidence tasks identify what must be clarified next.