<gsd-version v="1.12.4" />
|
|
|
|
<gsd-arguments>
|
|
<settings><keep-extra-args /></settings>
|
|
</gsd-arguments>
|
|
|
|
<gsd-execute>
|
|
<shell command="pi-gsd-tools">
|
|
<args>
|
|
<arg string="state" />
|
|
<arg string="reconcile" />
|
|
<arg string="--raw" />
|
|
</args>
|
|
<outs>
|
|
<suppress-errors />
|
|
<out type="string" name="reconcile-result" />
|
|
</outs>
|
|
</shell>
|
|
<shell command="pi-gsd-tools">
|
|
<args>
|
|
<arg string="roadmap" />
|
|
<arg string="analyze" />
|
|
<arg string="--raw" />
|
|
</args>
|
|
<outs>
|
|
<out type="string" name="roadmap" />
|
|
</outs>
|
|
</shell>
|
|
<shell command="pi-gsd-tools">
|
|
<args>
|
|
<arg string="state" />
|
|
<arg string="json" />
|
|
<arg string="--raw" />
|
|
</args>
|
|
<outs>
|
|
<out type="string" name="state" />
|
|
</outs>
|
|
</shell>
|
|
<shell command="pi-gsd-tools">
|
|
<args>
|
|
<arg string="config-get" />
|
|
<arg string="workflow.discuss_mode" />
|
|
<arg string="--raw" />
|
|
</args>
|
|
<outs>
|
|
<suppress-errors />
|
|
<out type="string" name="config" />
|
|
</outs>
|
|
</shell>
|
|
</gsd-execute>
|
|
|
|
## Context (pre-injected)
|
|
|
|
**Roadmap:**
|
|
<gsd-paste name="roadmap" />
|
|
|
|
**State:**
|
|
<gsd-paste name="state" />
|
|
|
|
<purpose>
|
|
Check project progress, summarize recent work and what's ahead, then intelligently route to the next action - either executing an existing plan or creating the next one. Provides situational awareness before continuing work.
|
|
</purpose>
|
|
|
|
<required_reading>
|
|
Read all files referenced by the invoking prompt's execution_context before starting.
|
|
</required_reading>
|
|
|
|
<process>
|
|
|
|
<step name="init_context">
|
|
**Load progress context (paths only):**
|
|
|
|
<!-- Context pre-injected above via WXP - variables available via <gsd-paste name="..."> -->
|
|
|
|
Extract from init JSON: `project_exists`, `roadmap_exists`, `state_exists`, `phases`, `current_phase`, `next_phase`, `milestone_version`, `completed_count`, `phase_count`, `paused_at`, `state_path`, `roadmap_path`, `project_path`, `config_path`.
|
|
|
|
```bash
|
|
DISCUSS_MODE=$(pi-gsd-tools config-get workflow.discuss_mode 2>/dev/null || echo "discuss")
|
|
```
|
|
|
|
If `project_exists` is false (no `.planning/` directory):
|
|
|
|
```
|
|
No planning structure found.
|
|
|
|
Run /gsd-new-project to start a new project.
|
|
```
|
|
|
|
Exit.
|
|
|
|
If missing STATE.md: suggest `/gsd-new-project`.
|
|
|
|
**If ROADMAP.md missing but PROJECT.md exists:**
|
|
|
|
This means a milestone was completed and archived. Go to **Route F** (between milestones).
|
|
|
|
If missing both ROADMAP.md and PROJECT.md: suggest `/gsd-new-project`.
|
|
</step>
|
|
|
|
<step name="load">
|
|
**Use structured extraction from gsd-tools:**
|
|
|
|
Instead of reading full files, use targeted tools to get only the data needed for the report:
|
|
- `ROADMAP=$(pi-gsd-tools roadmap analyze)`
|
|
- `STATE=$(pi-gsd-tools state-snapshot)`
|
|
|
|
This minimizes orchestrator context usage.
|
|
</step>
|
|
|
|
<step name="analyze_roadmap">
|
|
**Get comprehensive roadmap analysis (replaces manual parsing):**
|
|
|
|
```bash
|
|
ROADMAP=$(pi-gsd-tools roadmap analyze)
|
|
```
|
|
|
|
This returns structured JSON with:
|
|
- All phases with disk status (complete/partial/planned/empty/no_directory)
|
|
- Goal and dependencies per phase
|
|
- Plan and summary counts per phase
|
|
- Aggregated stats: total plans, summaries, progress percent
|
|
- Current and next phase identification
|
|
|
|
Use this instead of manually reading/parsing ROADMAP.md.
|
|
</step>
|
|
|
|
<step name="recent">
|
|
**Gather recent work context:**
|
|
|
|
- Find the 2-3 most recent SUMMARY.md files
|
|
- Use `summary-extract` for efficient parsing:
|
|
```bash
|
|
pi-gsd-tools summary-extract <path> --fields one_liner
|
|
```
|
|
- This shows "what we've been working on"
|
|
</step>
|
|
|
|
<step name="position">
|
|
**Parse current position from init context and roadmap analysis:**
|
|
|
|
- Use `current_phase` and `next_phase` from `$ROADMAP`
|
|
- Note `paused_at` if work was paused (from `$STATE`)
|
|
- Count pending todos: use `init todos` or `list-todos`
|
|
- Check for active debug sessions: `(ls .planning/debug/*.md 2>/dev/null || true) | grep -v resolved | wc -l`
|
|
</step>
|
|
|
|
<step name="report">
|
|
**Generate progress bar from gsd-tools, then present rich status report:**
|
|
|
|
```bash
|
|
# Get formatted progress bar
|
|
PROGRESS_BAR=$(pi-gsd-tools progress bar --raw)
|
|
```
|
|
|
|
Present:
|
|
|
|
```
|
|
# [Project Name]
|
|
|
|
**Progress:** {PROGRESS_BAR}
|
|
**Profile:** [quality/balanced/budget/inherit]
|
|
**Discuss mode:** {DISCUSS_MODE}
|
|
|
|
## Recent Work
|
|
- [Phase X, Plan Y]: [what was accomplished - 1 line from summary-extract]
|
|
- [Phase X, Plan Z]: [what was accomplished - 1 line from summary-extract]
|
|
|
|
## Current Position
|
|
Phase [N] of [total]: [phase-name]
|
|
Plan [M] of [phase-total]: [status]
|
|
CONTEXT: [✓ if has_context | - if not]
|
|
|
|
## Key Decisions Made
|
|
- [extract from $STATE.decisions[]]
|
|
- [e.g. jq -r '.decisions[].decision' from state-snapshot]
|
|
|
|
## Blockers/Concerns
|
|
- [extract from $STATE.blockers[]]
|
|
- [e.g. jq -r '.blockers[].text' from state-snapshot]
|
|
|
|
## Pending Todos
|
|
- [count] pending - /gsd-check-todos to review
|
|
|
|
## Active Debug Sessions
|
|
- [count] active - /gsd-debug to continue
|
|
(Only show this section if count > 0)
|
|
|
|
## What's Next
|
|
[Next phase/plan objective from roadmap analyze]
|
|
```
|
|
|
|
</step>
|
|
|
|
<step name="route">
|
|
**Determine next action based on verified counts.**
|
|
|
|
**Step 1: Count plans, summaries, and issues in current phase**
|
|
|
|
List files in the current phase directory:
|
|
|
|
```bash
|
|
(ls -1 .planning/phases/[current-phase-dir]/*-PLAN.md 2>/dev/null || true) | wc -l
|
|
(ls -1 .planning/phases/[current-phase-dir]/*-SUMMARY.md 2>/dev/null || true) | wc -l
|
|
(ls -1 .planning/phases/[current-phase-dir]/*-UAT.md 2>/dev/null || true) | wc -l
|
|
```
|
|
|
|
State: "This phase has {X} plans, {Y} summaries."
|
|
|
|
**Step 1.5: Check for unaddressed UAT gaps**
|
|
|
|
Check for UAT.md files with status "diagnosed" (has gaps needing fixes).
|
|
|
|
```bash
|
|
# Check for diagnosed UAT with gaps or partial (incomplete) testing
|
|
grep -l "status: diagnosed\|status: partial" .planning/phases/[current-phase-dir]/*-UAT.md 2>/dev/null || true
|
|
```
|
|
|
|
Track:
|
|
- `uat_with_gaps`: UAT.md files with status "diagnosed" (gaps need fixing)
|
|
- `uat_partial`: UAT.md files with status "partial" (incomplete testing)
|
|
|
|
**Step 1.6: Cross-phase health check**
|
|
|
|
Scan ALL phases in the current milestone for outstanding verification debt using the CLI (which respects milestone boundaries via `getMilestonePhaseFilter`):
|
|
|
|
```bash
|
|
DEBT=$(pi-gsd-tools audit-uat --raw 2>/dev/null)
|
|
```
|
|
|
|
Parse JSON for `summary.total_items` and `summary.total_files`.
|
|
|
|
Track: `outstanding_debt` - `summary.total_items` from the audit.
|
|
|
|
**If outstanding_debt > 0:** Add a warning section to the progress report output (in the `report` step), placed between "## What's Next" and the route suggestion:
|
|
|
|
```markdown
|
|
## Verification Debt ({N} files across prior phases)
|
|
|
|
| Phase | File | Issue |
|
|
| ------- | ---------- | ------------------------------------------------------------------------- |
|
|
| {phase} | {filename} | {pending_count} pending, {skipped_count} skipped, {blocked_count} blocked |
|
|
| {phase} | {filename} | human_needed - {count} items |
|
|
|
|
Review: `/gsd-audit-uat ${GSD_WS}` - full cross-phase audit
|
|
Resume testing: `/gsd-verify-work {phase} ${GSD_WS}` - retest specific phase
|
|
```
|
|
|
|
This is a WARNING, not a blocker - routing proceeds normally. The debt is visible so the user can make an informed choice.
|
|
|
|
**Step 2: Route based on counts**
|
|
|
|
| Condition | Meaning | Action |
|
|
| ------------------------------- | ----------------------- | ------------------- |
|
|
| uat_partial > 0 | UAT testing incomplete | Go to **Route E.2** |
|
|
| uat_with_gaps > 0 | UAT gaps need fix plans | Go to **Route E** |
|
|
| summaries < plans | Unexecuted plans exist | Go to **Route A** |
|
|
| summaries = plans AND plans > 0 | Phase complete | Go to Step 3 |
|
|
| plans = 0 | Phase not yet planned | Go to **Route B** |
|
|
|
|
---
|
|
|
|
**Route A: Unexecuted plan exists**
|
|
|
|
Find the first PLAN.md without matching SUMMARY.md.
|
|
Read its `<objective>` section.
|
|
|
|
```
|
|
---
|
|
|
|
## ▶ Next Up
|
|
|
|
**{phase}-{plan}: [Plan Name]** - [objective summary from PLAN.md]
|
|
|
|
`/gsd-execute-phase {phase} ${GSD_WS}`
|
|
|
|
<sub>`/new` first → fresh context window</sub>
|
|
|
|
---
|
|
```
|
|
|
|
---
|
|
|
|
**Route B: Phase needs planning**
|
|
|
|
Check if `{phase_num}-CONTEXT.md` exists in phase directory.
|
|
|
|
Check if current phase has UI indicators:
|
|
|
|
```bash
|
|
PHASE_SECTION=$(pi-gsd-tools roadmap get-phase "${CURRENT_PHASE}" 2>/dev/null)
|
|
PHASE_HAS_UI=$(echo "$PHASE_SECTION" | grep -qi "UI hint.*yes" && echo "true" || echo "false")
|
|
```
|
|
|
|
**If CONTEXT.md exists:**
|
|
|
|
```
|
|
---
|
|
|
|
## ▶ Next Up
|
|
|
|
**Phase {N}: {Name}** - {Goal from ROADMAP.md}
|
|
<sub>✓ Context gathered, ready to plan</sub>
|
|
|
|
`/gsd-plan-phase {phase-number} ${GSD_WS}`
|
|
|
|
<sub>`/new` first → fresh context window</sub>
|
|
|
|
---
|
|
```
|
|
|
|
**If CONTEXT.md does NOT exist AND phase has UI (`PHASE_HAS_UI` is `true`):**
|
|
|
|
```
|
|
---
|
|
|
|
## ▶ Next Up
|
|
|
|
**Phase {N}: {Name}** - {Goal from ROADMAP.md}
|
|
|
|
`/gsd-discuss-phase {phase}` - gather context and clarify approach
|
|
|
|
<sub>`/new` first → fresh context window</sub>
|
|
|
|
---
|
|
|
|
**Also available:**
|
|
- `/gsd-ui-phase {phase}` - generate UI design contract (recommended for frontend phases)
|
|
- `/gsd-plan-phase {phase}` - skip discussion, plan directly
|
|
- `/gsd-list-phase-assumptions {phase}` - see the agent's assumptions
|
|
|
|
---
|
|
```
|
|
|
|
**If CONTEXT.md does NOT exist AND phase has no UI:**
|
|
|
|
```
|
|
---
|
|
|
|
## ▶ Next Up
|
|
|
|
**Phase {N}: {Name}** - {Goal from ROADMAP.md}
|
|
|
|
`/gsd-discuss-phase {phase} ${GSD_WS}` - gather context and clarify approach
|
|
|
|
<sub>`/new` first → fresh context window</sub>
|
|
|
|
---
|
|
|
|
**Also available:**
|
|
- `/gsd-plan-phase {phase} ${GSD_WS}` - skip discussion, plan directly
|
|
- `/gsd-list-phase-assumptions {phase} ${GSD_WS}` - see the agent's assumptions
|
|
|
|
---
|
|
```
|
|
|
|
---
|
|
|
|
**Route E: UAT gaps need fix plans**
|
|
|
|
UAT.md exists with gaps (diagnosed issues). User needs to plan fixes.
|
|
|
|
```
|
|
---
|
|
|
|
## ⚠ UAT Gaps Found
|
|
|
|
**{phase_num}-UAT.md** has {N} gaps requiring fixes.
|
|
|
|
`/gsd-plan-phase {phase} --gaps ${GSD_WS}`
|
|
|
|
<sub>`/new` first → fresh context window</sub>
|
|
|
|
---
|
|
|
|
**Also available:**
|
|
- `/gsd-execute-phase {phase} ${GSD_WS}` - execute phase plans
|
|
- `/gsd-verify-work {phase} ${GSD_WS}` - run more UAT testing
|
|
|
|
---
|
|
```
|
|
|
|
---
|
|
|
|
**Route E.2: UAT testing incomplete (partial)**
|
|
|
|
UAT.md exists with `status: partial` - testing session ended before all items resolved.
|
|
|
|
```
|
|
---
|
|
|
|
## Incomplete UAT Testing
|
|
|
|
**{phase_num}-UAT.md** has {N} unresolved tests (pending, blocked, or skipped).
|
|
|
|
`/gsd-verify-work {phase} ${GSD_WS}` - resume testing from where you left off
|
|
|
|
<sub>`/new` first → fresh context window</sub>
|
|
|
|
---
|
|
|
|
**Also available:**
|
|
- `/gsd-audit-uat ${GSD_WS}` - full cross-phase UAT audit
|
|
- `/gsd-execute-phase {phase} ${GSD_WS}` - execute phase plans
|
|
|
|
---
|
|
```
|
|
|
|
---
|
|
|
|
**Step 3: Check milestone status (only when phase complete)**
|
|
|
|
Read ROADMAP.md and identify:
|
|
1. Current phase number
|
|
2. All phase numbers in the current milestone section
|
|
|
|
Count total phases and identify the highest phase number.
|
|
|
|
State: "Current phase is {X}. Milestone has {N} phases (highest: {Y})."
|
|
|
|
**Route based on milestone status:**
|
|
|
|
| Condition | Meaning | Action |
|
|
| ----------------------------- | ------------------ | ----------------- |
|
|
| current phase < highest phase | More phases remain | Go to **Route C** |
|
|
| current phase = highest phase | Milestone complete | Go to **Route D** |
|
|
|
|
---
|
|
|
|
**Route C: Phase complete, more phases remain**
|
|
|
|
Read ROADMAP.md to get the next phase's name and goal.
|
|
|
|
Check if next phase has UI indicators:
|
|
|
|
```bash
|
|
NEXT_PHASE_SECTION=$(pi-gsd-tools roadmap get-phase "$((Z+1))" 2>/dev/null)
|
|
NEXT_HAS_UI=$(echo "$NEXT_PHASE_SECTION" | grep -qi "UI hint.*yes" && echo "true" || echo "false")
|
|
```
|
|
|
|
**If next phase has UI (`NEXT_HAS_UI` is `true`):**
|
|
|
|
```
|
|
---
|
|
|
|
## ✓ Phase {Z} Complete
|
|
|
|
## ▶ Next Up
|
|
|
|
**Phase {Z+1}: {Name}** - {Goal from ROADMAP.md}
|
|
|
|
`/gsd-discuss-phase {Z+1}` - gather context and clarify approach
|
|
|
|
<sub>`/new` first → fresh context window</sub>
|
|
|
|
---
|
|
|
|
**Also available:**
|
|
- `/gsd-ui-phase {Z+1}` - generate UI design contract (recommended for frontend phases)
|
|
- `/gsd-plan-phase {Z+1}` - skip discussion, plan directly
|
|
- `/gsd-verify-work {Z}` - user acceptance test before continuing
|
|
|
|
---
|
|
```
|
|
|
|
**If next phase has no UI:**
|
|
|
|
```
|
|
---
|
|
|
|
## ✓ Phase {Z} Complete
|
|
|
|
## ▶ Next Up
|
|
|
|
**Phase {Z+1}: {Name}** - {Goal from ROADMAP.md}
|
|
|
|
`/gsd-discuss-phase {Z+1} ${GSD_WS}` - gather context and clarify approach
|
|
|
|
<sub>`/new` first → fresh context window</sub>
|
|
|
|
---
|
|
|
|
**Also available:**
|
|
- `/gsd-plan-phase {Z+1} ${GSD_WS}` - skip discussion, plan directly
|
|
- `/gsd-verify-work {Z} ${GSD_WS}` - user acceptance test before continuing
|
|
|
|
---
|
|
```
|
|
|
|
---
|
|
|
|
**Route D: Milestone complete**
|
|
|
|
```
|
|
---
|
|
|
|
## 🎉 Milestone Complete
|
|
|
|
All {N} phases finished!
|
|
|
|
## ▶ Next Up
|
|
|
|
**Complete Milestone** - archive and prepare for next
|
|
|
|
`/gsd-complete-milestone ${GSD_WS}`
|
|
|
|
<sub>`/new` first → fresh context window</sub>
|
|
|
|
---
|
|
|
|
**Also available:**
|
|
- `/gsd-verify-work ${GSD_WS}` - user acceptance test before completing milestone
|
|
|
|
---
|
|
```
|
|
|
|
---
|
|
|
|
**Route F: Between milestones (ROADMAP.md missing, PROJECT.md exists)**
|
|
|
|
A milestone was completed and archived. Ready to start the next milestone cycle.
|
|
|
|
Read MILESTONES.md to find the last completed milestone version.
|
|
|
|
```
|
|
---
|
|
|
|
## ✓ Milestone v{X.Y} Complete
|
|
|
|
Ready to plan the next milestone.
|
|
|
|
## ▶ Next Up
|
|
|
|
**Start Next Milestone** - questioning → research → requirements → roadmap
|
|
|
|
`/gsd-new-milestone ${GSD_WS}`
|
|
|
|
<sub>`/new` first → fresh context window</sub>
|
|
|
|
---
|
|
```
|
|
|
|
</step>
|
|
|
|
<step name="edge_cases">
|
|
**Handle edge cases:**
|
|
|
|
- Phase complete but next phase not planned → offer `/gsd-plan-phase [next] ${GSD_WS}`
|
|
- All work complete → offer milestone completion
|
|
- Blockers present → highlight before offering to continue
|
|
- Handoff file exists → mention it, offer `/gsd-resume-work ${GSD_WS}`
|
|
</step>
|
|
|
|
</process>
|
|
|
|
<success_criteria>
|
|
|
|
- [ ] Rich context provided (recent work, decisions, issues)
|
|
- [ ] Current position clear with visual progress
|
|
- [ ] What's next clearly explained
|
|
- [ ] Smart routing: /gsd-execute-phase if plans exist, /gsd-plan-phase if not
|
|
- [ ] User confirms before any action
|
|
- [ ] Seamless handoff to appropriate gsd command
|
|
</success_criteria>
|